In The State of Bihar through the Principal Secretary, Rural Works Department, Bihar & Ors. vs. Lal Jha (2025), Patna High Court's Division Bench of Acting Chief Justice Sudhir Singh and Justice Rajesh Kumar Verma delivered a 5-page long judgement dated October 31, 2025, wherein, upheld the 5-page long order dated September 23, 2024 by Justice A. Abhishek Reddy in Lal Jha vs. The State of Bihar through the Principal Secretary, Rural Works Department, Bihar (2024). The judgement was authored by Justice Singh. In his third judgement as Acting Chief Justice , he concluded:"....we find no reason to interfere in the order of the learned Single Judge. affirmed, and the appeal is, accordingly, dismissed." The other 4 respondents were: The Chief Engineer, Rural Works Department, Patna, Additional Chief Executive Officer, Rural Works Department, Patna, Superintending Engineer, Rural Works Department, Works Circle, Darbhanga and Executive Engineer, Rural Woks Department, Works Division, Madhubani.
The intra court appeal was filed against Justice Reddy's order whereby the he had issued direction to the authorities to calculate the amount payable to the petitioner towards the maintenance for the year 2021-22 to 2022-23 as expeditiously as possible, preferably within a period of eight weeks from the date of the receipt of the copy of the order and pay the same. It was further clarified that, in case, the amounts are not paid by the authority within the stipulated time, the petitioner would be entitled to simple interest at the rate of 8% per annum from the date of the submission of the bills till the date of actual payment to the petitioner.
Pursuant to the notice inviting tender (NIT) floated under the authority of the respondent department, the petitioner was allotted the construction and five years maintenance work of the road, namely, Champa Laxmipur and Jadaha under the Scheme New Maintenance Policy MR 3054 vide Agreement No. 90MBD/2020-21 dated 19.09.2020. The respondent-petitioners were paid the maintenance cost for the year 2023-24. However, they were not paid the maintenance cost for the year 2021-22 and 2022-23. The respondent-petitioners had contented before the Writ Court that they had completed the construction work in the year 2021 itself and ought to be paid the maintenance cost for the year 2021-22 and 2022-23.
Justice Reddy had observed: “5. Admittedly, as seen from the record, the petitioner was entrusted with the work of laying of the roads for the areas i.e. Jadaha Tole Road measuring length 1.130 Kilometres and Champa-laxmipur measuring length 19.750 Kilometres. The petitioner after completion of the work was entitled for maintenance of the roads for a period of five years under the said agreement. The respondents are disputing the date of completion of the work which according to the petitioner was completed on 15.06.2021, whereas the respondents are stating that the work was completed only in the year 2023. In the counter affidavit, it is stated that the works were completed only in the year 2023, however, it is to be noted that in the said counter affidavit the factum of entering into the contract in the year 2020 is not disputed and also the fact that the completion of the work was within a period of nine months from the date of the commencement of the work i.e. from 19.09.2020 has also not been disputed by the authorities. When they themselves are stating that the agreement was entered on 19.09.2020 and the works were commenced from 19.09.2020 to be completed within a period of nine months from the date of commencement of the work, the question of completing the works in the year 2023 does not arise."
The counsel for the petitioner pointed out that in case, the petitioner had completed the work only in the month of July 2023 as alleged by the respondents, the petitioner could have been subjected to penalty for not completing the work within the stipulated time and also black-listing. However, the same is not the case, moreover, there is no averments in the counter affidavit to the effect that the petitioner at any point of time was given any extension of time. Further, it is to be noted that merely because the Management Information System (MIS) shows the completion of work as 15.07.2023, the same cannot be a ground for denying the payment and penalize the petitioner for the same. It was pointed out by the counsel for the petitioner that the measurement book filed by the respondents themselves shows that the works were completed in the year, 2021.
The High Court recorded:"5. From perusal of records of the case, it is apparent that the concerned Department themselves have stated in their counter-affidavit that the agreement was entered into on 19.09.2020, and the work commenced from 19.09.2020. Further, it has been stated in the counter-affidavit before the Writ Court that the date of completion of work was 9 months from the date of commencement of the work. As such, the appellants have themselves stated that the work was completed within the stipulated period of time.
In Lal Jha vs. The State of Bihar through the Principal Secretary, Rural Works Department, Patna & Ors. (2024), Justice Reddy had concluded:"....the stand taken by the authorities that the petitioner has completed the work only in the month of July, 2023 and, therefore, he is not entitled for the year 2021-22 to 2022-23 is without any legal basis and contrary to the record. The authorities have directed to calculate the amount payable to the petitioner towards the maintenance for the year 2021-22 to 2022-23 as expeditiously as possible preferably within a period of eight weeks from the date of the receipt of the copy of this order and pay the same. It is further clarified that, in case, the amounts are not paid by the authority within the stipulated time, the petitioner would be entitled to simple interest at the rate of 8% per annum from the date of the submission of the bills till the date of actual payment to the petitioner." With these directions, the writ petition was allowed to the extent indicated.